nerdexam
CompTIA

PK0-003 · Question #104

The design activity of a project has the following cost attributes: PV = 100,000 EV = 20,000 AC = 90,000 Based on this scenario, calculate the schedule variance.

The correct answer is A. -80,000. Given the Planned Value (PV), Earned Value (EV), and Actual Cost (AC) for a project design activity, the task is to calculate the schedule variance.

Project management concepts

Question

The design activity of a project has the following cost attributes:

PV = 100,000 EV = 20,000 AC = 90,000 Based on this scenario, calculate the schedule variance.

Options

  • A-80,000
  • B-70,000
  • C10,000
  • D120,000

How the community answered

(40 responses)
  • A
    78% (31)
  • B
    8% (3)
  • C
    3% (1)
  • D
    13% (5)

Why each option

Given the Planned Value (PV), Earned Value (EV), and Actual Cost (AC) for a project design activity, the task is to calculate the schedule variance.

A-80,000Correct

Schedule Variance (SV) is calculated as Earned Value (EV) minus Planned Value (PV). In this scenario, SV = EV - PV = 20,000 - 100,000 = -80,000. A negative schedule variance indicates that less work has been completed than planned at this point.

B-70,000

This value might result from incorrect calculations or misinterpreting the formula, such as EV - AC, which would be Cost Variance.

C10,000

This value does not correspond to the correct schedule variance calculation using the provided figures.

D120,000

This value does not correspond to the correct schedule variance calculation and might result from incorrect addition or subtraction of the given parameters.

Concept tested: Earned Value Management (EVM) - Schedule Variance calculation

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/earned-value-management-calculations

Topics

#earned value management#schedule variance calculation#project cost control

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice