nerdexam
CompTIA

PK0-003 · Question #102

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure. This type of analysis is an example of which of the followi

The correct answer is C. Schedule variance. The project manager is comparing the earned value of work completed to the planned value, expressed in monetary terms.

Project management concepts

Question

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure. This type of analysis is an example of which of the following?

Options

  • ACost performance index
  • BRisk mitigation
  • CSchedule variance
  • DCost variance

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    17% (4)
  • C
    75% (18)
  • D
    4% (1)

Why each option

The project manager is comparing the earned value of work completed to the planned value, expressed in monetary terms.

ACost performance index

Cost performance index (CPI) is a ratio of earned value to actual costs, indicating the efficiency of budget utilization, not the difference between earned and planned value.

BRisk mitigation

Risk mitigation involves strategies to reduce the impact or probability of risks, and is unrelated to earned value management calculations.

CSchedule varianceCorrect

Schedule Variance (SV) is a measure of schedule performance expressed as the difference between the Earned Value (EV) and the Planned Value (PV), typically calculated as SV = EV - PV. When represented in a dollar figure, it indicates how much value has been earned relative to what was planned at a given point in time.

DCost variance

Cost variance (CV) is the difference between earned value and actual costs (CV = EV - AC), indicating budget performance, not schedule performance relative to planned value.

Concept tested: Earned Value Management (EVM) - Schedule Variance (SV)

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/earned-value-management-calculations

Topics

#earned value management#schedule variance#cost performance analysis

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice