nerdexam
CompTIA

PK0-003 · Question #101

The project manager has had a large number of change requests approved by the project steering committee, but has been given no extra time to deliver the project. Which of the following schedule compr

The correct answer is B. Crashing. To complete a project on time despite approved changes and no time extension, the project manager should use schedule compression techniques.

Project management concepts

Question

The project manager has had a large number of change requests approved by the project steering committee, but has been given no extra time to deliver the project. Which of the following schedule compression techniques should be used by the project manager?

Options

  • ARescheduling
  • BCrashing
  • CRebaselining
  • DControl scope

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    80% (24)
  • C
    3% (1)
  • D
    13% (4)

Why each option

To complete a project on time despite approved changes and no time extension, the project manager should use schedule compression techniques.

ARescheduling

Rescheduling might involve adjusting task dates, but it doesn't inherently compress the schedule when no extra time is given and scope has increased.

BCrashingCorrect

Crashing is a schedule compression technique that involves adding resources to critical path activities to shorten the overall project duration at an increased cost. In this scenario, with no extra time but approved changes, crashing helps meet the deadline by accelerating specific tasks.

CRebaselining

Rebaselining involves formally approving a new project baseline, often due to significant changes, but it is not a direct technique for compressing the schedule itself.

DControl scope

Control scope is a process to manage project scope, ensuring that only approved work is performed, rather than a technique to compress the schedule.

Concept tested: Project schedule compression techniques (Crashing)

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/schedule-project-schedule-compression-techniques

Topics

#schedule compression#crashing#project schedule

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice