nerdexam
PMIPMI

PGMP · Question #544

PGMP Question #544: Real Exam Question with Answer & Explanation

Sign in or unlock PGMP to reveal the answer and full explanation for question #544. The question stem and answer options stay visible for context.

Program Benefits Management

Question

Near the end of an ongoing project, the program manager is terminated due to underperformance and a new program manager joins the team. The program's last component project will go live in one week. What must the new program manager do before program closure?

Options

  • AReview the benefits management plan to ensure that the first component project launched met
  • BAsk the program steering committee to allow program closure to start immediately following the
  • CBegin to collect lessons learned from all stakeholders, and prepare mitigation strategies in
  • DWork with the program sponsor to identify who is responsible for benefits sustainment, and identify

Unlock PGMP to see the answer

You've previewed enough free PGMP questions. Unlock PGMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Program Closure#Benefits Sustainment#Program Transition#Stakeholder Collaboration
Full PGMP PracticeBrowse All PGMP Questions