PGMP · Question #544
Near the end of an ongoing project, the program manager is terminated due to underperformance and a new program manager joins the team. The program's last component project will go live in one week. W
The correct answer is D. Work with the program sponsor to identify who is responsible for benefits sustainment, and identify. Before a program can close, the new program manager must ensure that the benefits the program was created to deliver will continue to be realized after closure. Choice D is correct because identifying who is responsible for benefits sustainment and establishing transition activit
Question
Near the end of an ongoing project, the program manager is terminated due to underperformance and a new program manager joins the team. The program's last component project will go live in one week. What must the new program manager do before program closure?
Options
- AReview the benefits management plan to ensure that the first component project launched met
- BAsk the program steering committee to allow program closure to start immediately following the
- CBegin to collect lessons learned from all stakeholders, and prepare mitigation strategies in
- DWork with the program sponsor to identify who is responsible for benefits sustainment, and identify
How the community answered
(32 responses)- A9% (3)
- B3% (1)
- C19% (6)
- D69% (22)
Explanation
Before a program can close, the new program manager must ensure that the benefits the program was created to deliver will continue to be realized after closure. Choice D is correct because identifying who is responsible for benefits sustainment and establishing transition activities are prerequisite closure steps - without a designated owner for ongoing benefits, value gained from the program can quickly erode. Choice A focuses only on the first component rather than the full program and is backward-looking. Choice B asks for permission to start closure prematurely, before ensuring transition readiness. Choice C (collecting lessons learned and mitigation strategies) is also part of closure, but it comes after the critical benefits handoff responsibilities are established, making D the most urgent first action.
Topics
Community Discussion
No community discussion yet for this question.