nerdexam
PMI

PGMP · Question #544

Near the end of an ongoing project, the program manager is terminated due to underperformance and a new program manager joins the team. The program's last component project will go live in one week. W

The correct answer is D. Work with the program sponsor to identify who is responsible for benefits sustainment, and identify. Before a program can close, the new program manager must ensure that the benefits the program was created to deliver will continue to be realized after closure. Choice D is correct because identifying who is responsible for benefits sustainment and establishing transition activit

Program Benefits Management

Question

Near the end of an ongoing project, the program manager is terminated due to underperformance and a new program manager joins the team. The program's last component project will go live in one week. What must the new program manager do before program closure?

Options

  • AReview the benefits management plan to ensure that the first component project launched met
  • BAsk the program steering committee to allow program closure to start immediately following the
  • CBegin to collect lessons learned from all stakeholders, and prepare mitigation strategies in
  • DWork with the program sponsor to identify who is responsible for benefits sustainment, and identify

How the community answered

(32 responses)
  • A
    9% (3)
  • B
    3% (1)
  • C
    19% (6)
  • D
    69% (22)

Explanation

Before a program can close, the new program manager must ensure that the benefits the program was created to deliver will continue to be realized after closure. Choice D is correct because identifying who is responsible for benefits sustainment and establishing transition activities are prerequisite closure steps - without a designated owner for ongoing benefits, value gained from the program can quickly erode. Choice A focuses only on the first component rather than the full program and is backward-looking. Choice B asks for permission to start closure prematurely, before ensuring transition readiness. Choice C (collecting lessons learned and mitigation strategies) is also part of closure, but it comes after the critical benefits handoff responsibilities are established, making D the most urgent first action.

Topics

#Program Closure#Benefits Sustainment#Program Transition#Stakeholder Collaboration

Community Discussion

No community discussion yet for this question.

Full PGMP Practice