PGMP · Question #532
Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?
The correct answer is A. Program performance report. A Program Performance Report is the primary document used to communicate a program's overall health to stakeholders. It consolidates information about program and component status, schedule performance, cost data, risk exposure, issues, and other relevant metrics into a single…
Question
Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?
Options
- AProgram performance report
- BCommunications management plan
- CCommunications log updates
- DInformation gathering and retrieval system
How the community answered
(54 responses)- A87% (47)
- B2% (1)
- C7% (4)
- D4% (2)
Explanation
A Program Performance Report is the primary document used to communicate a program's overall health to stakeholders. It consolidates information about program and component status, schedule performance, cost data, risk exposure, issues, and other relevant metrics into a single reporting artifact. The Communications Management Plan (B) describes how communications will be conducted but does not itself contain status data. A Communications Log (C) tracks communication events but does not aggregate performance data. An Information Gathering and Retrieval System (D) is a tool or technology used to store and access information, not a reporting output.