nerdexam
PMIPMI

PGMP · Question #439

PGMP Question #439: Real Exam Question with Answer & Explanation

The correct answer is D: Program activities, component activities, and all other work. See the full explanation below for the reasoning.

Program Life Cycle Management

Question

In preparation for the development and submission of the program master schedule to a client, the program manager meets with the component project manager and master program scheduler to discuss the work breakdown structure (WBS). During the meeting, the master scheduler indicates that the master program schedule should include which of the following?

Options

  • AProgram benefits and all component project activities
  • BComponent resources and their activity assignment/responsibility metrics
  • CProgram-level activities and integrated component projects
  • DProgram activities, component activities, and all other work

Topics

#Program Schedule#Work Breakdown Structure (WBS)#Program Planning#Scope Definition

Community Discussion

No community discussion yet for this question.

Full PGMP PracticeBrowse All PGMP Questions