Program Life Cycle Management
Question
In preparation for the development and submission of the program master schedule to a client, the program manager meets with the component project manager and master program scheduler to discuss the work breakdown structure (WBS). During the meeting, the master scheduler indicates that the master program schedule should include which of the following?
Options
- AProgram benefits and all component project activities
- BComponent resources and their activity assignment/responsibility metrics
- CProgram-level activities and integrated component projects
- DProgram activities, component activities, and all other work
Topics
#Program Schedule#Work Breakdown Structure (WBS)#Program Planning#Scope Definition