PGMP · Question #440
A program manager has a multiple-project program that is scheduled to be completed by year's end. During the program delivery phases of the projects, several mandatory changes are identified that…
The correct answer is D. Submit a change request to extend the program schedule. When mandatory changes are identified that will extend the program's completion date, the program manager must follow the formal change control process by submitting a change request. Mandatory changes cannot be absorbed silently-they require documented review, approval, and…
Question
A program manager has a multiple-project program that is scheduled to be completed by year's end. During the program delivery phases of the projects, several mandatory changes are identified that would extend the program's completion date. What is the next step for the program manager?
Options
- AApply resource leveling to ensure the program is completed on schedule
- BUpdate the schedule to reflect the extended completion date
- CAdjust working hours to ensure the program is completed on schedule
- DSubmit a change request to extend the program schedule
How the community answered
(46 responses)- A4% (2)
- B13% (6)
- C7% (3)
- D76% (35)
Explanation
When mandatory changes are identified that will extend the program's completion date, the program manager must follow the formal change control process by submitting a change request. Mandatory changes cannot be absorbed silently-they require documented review, approval, and baseline updates through the program's governance process. Option A (resource leveling) and Option C (adjusting working hours) are schedule compression techniques that may not be feasible for mandatory scope-driven changes, and they do not address the formal governance requirement. Option B (simply updating the schedule) skips the required approval process. Change requests ensure that the schedule extension is properly authorized, communicated, and recorded in the program management plan.