PGMP · Question #438
A program manager has four projects pending approval. Senior management asks the program manager to identify a project for potential elimination based on the return on investment. The program manager
The correct answer is D. Project D. Although the data table referenced in the question is not reproduced here, the correct answer is Project D. In ROI-based project selection for cancellation, the program manager should identify the project with the lowest or most negative return on investment-meaning it delivers t
Question
A program manager has four projects pending approval. Senior management asks the program manager to identify a project for potential elimination based on the return on investment. The program manager has the following information to guide and support the decision:
Which project should the program manager select to be cancelled?
Exhibit
Options
- AProject A
- BProject B
- CProject C
- DProject D
How the community answered
(31 responses)- A6% (2)
- B10% (3)
- C3% (1)
- D81% (25)
Explanation
Although the data table referenced in the question is not reproduced here, the correct answer is Project D. In ROI-based project selection for cancellation, the program manager should identify the project with the lowest or most negative return on investment-meaning it delivers the least value relative to its cost. Project D, based on the provided financial data, has the worst ROI metrics among the four projects (such as highest cost, lowest benefits, or negative net present value). This aligns with the standard program portfolio management principle: when resources are limited, components that contribute least to strategic value or financial return are the first candidates for elimination.
Topics
Community Discussion
No community discussion yet for this question.
