PGMP · Question #42
A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is running late due to some vendor delays; the program is only 30 percent complete though it was…
The correct answer is C. $991,667. This requires Estimate to Complete (ETC) using Earned Value Management. Step 1 - Calculate Earned Value (EV): EV = BAC × % complete = $1,250,000 × 0.30 = $375,000. Step 2 - Calculate Cost Performance Index (CPI): CPI = EV / AC = $375,000 / $425,000 ≈ 0.8824. Step 3 - Calculate…
Question
A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is running late due to some vendor delays; the program is only 30 percent complete though it was scheduled to be 45 percent at this time. Based on this information how much more money will this program need to finish?
Options
- A$978,445
- B$919,325
- C$991,667
- D$987,544
How the community answered
(30 responses)- A13% (4)
- B3% (1)
- C80% (24)
- D3% (1)
Explanation
This requires Estimate to Complete (ETC) using Earned Value Management. Step 1 - Calculate Earned Value (EV): EV = BAC × % complete = $1,250,000 × 0.30 = $375,000. Step 2 - Calculate Cost Performance Index (CPI): CPI = EV / AC = $375,000 / $425,000 ≈ 0.8824. Step 3 - Calculate ETC: ETC = (BAC − EV) / CPI = ($1,250,000 − $375,000) / 0.8824 = $875,000 / 0.8824 ≈ $991,667. Because the program is spending more than it is earning (CPI < 1), it will need more money than the remaining planned budget to finish, which is why the answer ($991,667) exceeds the simple remaining balance of $875,000.
Topics
Community Discussion
No community discussion yet for this question.