Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured she has set several requirements for the…
The correct answer is A. Screening system. A screening system establishes minimum, non-negotiable requirements that vendors must meet just to be considered for a contract. Requiring at least four licensed electricians is a pass/fail threshold - vendors who don't meet it are immediately disqualified. This is the…
Question
Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured she has set several requirements for the vendors to participate. The chief among these requirements is a vendor must have at least four licensed electricians in his team. This requirement for four licensed electricians is an example of which one of the following terms?
Options
- AScreening system
- BScoring model
- CVendor analysis requirements
- DEvaluation criteria
How the community answered
(24 responses)- A79% (19)
- B13% (3)
- C4% (1)
- D4% (1)
Explanation
A screening system establishes minimum, non-negotiable requirements that vendors must meet just to be considered for a contract. Requiring at least four licensed electricians is a pass/fail threshold - vendors who don't meet it are immediately disqualified. This is the definition of a screening system. A scoring model (B) would assign points to vendor attributes and rank them; it doesn't eliminate anyone outright. Evaluation criteria (D) is a broader term that encompasses how proposals are assessed overall, while a screening system is a specific subset used for baseline qualification filtering.