PGMP · Question #388
A Project Manager is in the execution phase of a highly visible project and a major milestone is due in three weeks. The Project Manager has discovered that a vendor's deliverable for this milestone w
The correct answer is B. Meet with the team and brainstorm how to create a workaround for this problem. A vendor's deliverable will be five weeks late with a milestone due in three weeks, creating a schedule gap. The PM should work proactively with the team to develop a workaround.
Question
A Project Manager is in the execution phase of a highly visible project and a major milestone is due in three weeks. The Project Manager has discovered that a vendor's deliverable for this milestone will be five weeks late. What should the Project Manager do?
Options
- ADo not report this problem in the status meeting
- BMeet with the team and brainstorm how to create a workaround for this problem
- CHalt all payments to the vendor until the deliverable is received
- DReport the status of the missed milestone
How the community answered
(23 responses)- A4% (1)
- B83% (19)
- C4% (1)
- D9% (2)
Why each option
A vendor's deliverable will be five weeks late with a milestone due in three weeks, creating a schedule gap. The PM should work proactively with the team to develop a workaround.
Hiding a known risk to a major milestone from status meetings is a violation of transparency and professional responsibility.
With the milestone due in three weeks and the vendor five weeks behind, the PM must proactively engage the team to identify a workaround - such as resequencing work, using partial deliverables, or finding an alternate source - to mitigate the impact. This reflects PMI's emphasis on proactive issue resolution during project execution. Brainstorming with the team leverages collective expertise to find the most viable path forward before the milestone is missed.
Halting payments to the vendor may be a contractual remedy but does not solve the immediate schedule problem and should only follow formal contract dispute processes.
Simply reporting the missed milestone without taking corrective action is reactive rather than proactive and leaves the project without a recovery plan.
Concept tested: Proactive workaround planning during project execution
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.