PMIPMI
PGMP · Question #389
PGMP Question #389: Real Exam Question with Answer & Explanation
The correct answer is B: Meet with the team and brainstorm how to create a workaround for this problem. See the full explanation below for the reasoning.
Program Life Cycle Management
Question
A Project Manager is in the execution phase of a highly visible project and a major milestone is due in one week. The Project Manager has discovered that a vendor's deliverable for this milestone will be two weeks late. What should the Project Manager do?
Options
- ADo not report this problem in the status meeting
- BMeet with the team and brainstorm how to create a workaround for this problem
- CHalt all payments to the vendor until the deliverable is received
- DReport the status of the missed milestone
Topics
#Issue Management#Problem Solving#Team Collaboration#Risk Mitigation
Community Discussion
No community discussion yet for this question.