nerdexam
PMI

PGMP · Question #389

A Project Manager is in the execution phase of a highly visible project and a major milestone is due in one week. The Project Manager has discovered that a vendor's deliverable for this milestone…

The correct answer is B. Meet with the team and brainstorm how to create a workaround for this problem. A vendor's deliverable will be two weeks late with the milestone due in one week, making a delay unavoidable. The PM should immediately work with the team to find a workaround.

Program Life Cycle Management

Question

A Project Manager is in the execution phase of a highly visible project and a major milestone is due in one week. The Project Manager has discovered that a vendor's deliverable for this milestone will be two weeks late. What should the Project Manager do?

Options

  • ADo not report this problem in the status meeting
  • BMeet with the team and brainstorm how to create a workaround for this problem
  • CHalt all payments to the vendor until the deliverable is received
  • DReport the status of the missed milestone

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    76% (28)
  • C
    16% (6)
  • D
    3% (1)

Why each option

A vendor's deliverable will be two weeks late with the milestone due in one week, making a delay unavoidable. The PM should immediately work with the team to find a workaround.

ADo not report this problem in the status meeting

Concealing a known issue that will cause a missed milestone is unethical and violates PMI's standards for transparent stakeholder communication.

BMeet with the team and brainstorm how to create a workaround for this problemCorrect

When a vendor deliverable will arrive two weeks after a one-week deadline, the PM must urgently engage the team to brainstorm workarounds - such as partial acceptance, parallel processing, or substitution - to minimize the milestone impact. This proactive approach demonstrates PMI's expectation that PMs actively manage and mitigate risks rather than simply documenting them. Acting immediately gives the team the maximum available time to implement a viable solution.

CHalt all payments to the vendor until the deliverable is received

Halting vendor payments is a punitive contractual action that does not address the immediate schedule crisis and requires formal process to execute.

DReport the status of the missed milestone

Reporting the missed milestone without a recovery plan is passive management that fails the team and stakeholders who expect proactive problem resolution.

Concept tested: Urgent workaround planning for imminent milestone risk

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Issue Management#Problem Solving#Team Collaboration#Risk Mitigation

Community Discussion

No community discussion yet for this question.

Full PGMP Practice