nerdexam
PMIPMI

PGMP · Question #389

PGMP Question #389: Real Exam Question with Answer & Explanation

The correct answer is B: Meet with the team and brainstorm how to create a workaround for this problem. See the full explanation below for the reasoning.

Program Life Cycle Management

Question

A Project Manager is in the execution phase of a highly visible project and a major milestone is due in one week. The Project Manager has discovered that a vendor's deliverable for this milestone will be two weeks late. What should the Project Manager do?

Options

  • ADo not report this problem in the status meeting
  • BMeet with the team and brainstorm how to create a workaround for this problem
  • CHalt all payments to the vendor until the deliverable is received
  • DReport the status of the missed milestone

Topics

#Issue Management#Problem Solving#Team Collaboration#Risk Mitigation

Community Discussion

No community discussion yet for this question.

Full PGMP PracticeBrowse All PGMP Questions