PGMP · Question #339

Molly is the program manager for her organization. She is creating a document that defines the benefits the program will create for her organization once the program has been completed. What document

The correct answer is C. Program benefits statement. A Program Benefits Statement defines what benefits the program will deliver to the organization upon completion - it describes the expected outcomes and their value. It is distinct from the Program Benefits Realization Plan, which outlines HOW and WHEN those benefits will be achi

Benefits Management

Question

Molly is the program manager for her organization. She is creating a document that defines the benefits the program will create for her organization once the program has been completed. What document is Molly writing?

Options

  • AProgram charter
  • BProgram benefits realization plan
  • CProgram benefits statement
  • DProgram scope statement

How the community answered

(23 responses)
  • B
    4% (1)
  • C
    96% (22)

Explanation

A Program Benefits Statement defines what benefits the program will deliver to the organization upon completion - it describes the expected outcomes and their value. It is distinct from the Program Benefits Realization Plan, which outlines HOW and WHEN those benefits will be achieved and measured. The program charter authorizes the program, and the scope statement defines what work is included. Since Molly is documenting the benefits the program will create (not how to realize them), the correct document is the Program Benefits Statement. Answer: C.

Topics

#Program Benefits Management#Program Documentation#Benefits Statement