nerdexam
PMIPMI

PGMP · Question #331

PGMP Question #331: Real Exam Question with Answer & Explanation

The correct answer is C: Project Management Information System. See the full explanation below for the reasoning.

Life Cycle Management

Question

Donna is the project manager for her organization. She is preparing a plan to manage changes to the project should changes be requested. Her change management plan defines the process for documenting, tracking, and determining if the changes should be approved or declined. What system is considered the parent of the change control system documented in Donna's plan?

Options

  • AQuality Management System
  • BChange Control System
  • CProject Management Information System
  • DIntegrated Change Control System

Topics

#Project Management Information System#Change Control System#Integrated Change Control#Project Management Planning

Community Discussion

No community discussion yet for this question.

Full PGMP PracticeBrowse All PGMP Questions