PMIPMI
PGMP · Question #331
PGMP Question #331: Real Exam Question with Answer & Explanation
The correct answer is C: Project Management Information System. See the full explanation below for the reasoning.
Life Cycle Management
Question
Donna is the project manager for her organization. She is preparing a plan to manage changes to the project should changes be requested. Her change management plan defines the process for documenting, tracking, and determining if the changes should be approved or declined. What system is considered the parent of the change control system documented in Donna's plan?
Options
- AQuality Management System
- BChange Control System
- CProject Management Information System
- DIntegrated Change Control System
Topics
#Project Management Information System#Change Control System#Integrated Change Control#Project Management Planning
Community Discussion
No community discussion yet for this question.