You are the program manager for your organization. Management has asked you to create a document that will capture the stakeholders concerns, perceived threats, and specific objectives about the progr

The correct answer is B. Scope statement. The program scope statement is a comprehensive document that defines the program's deliverables and objectives, and also captures stakeholder concerns, constraints, assumptions, perceived threats, and exclusions. It aligns stakeholder expectations with the program's intended outc

Life Cycle Management

Question

You are the program manager for your organization. Management has asked you to create a document that will capture the stakeholders concerns, perceived threats, and specific objectives about the program and its projects. What document is management asking you to create in this instance?

Options

  • ABusiness case
  • BScope statement
  • CRequirements document
  • DProject charter

How the community answered

(33 responses)
  • A
    9% (3)
  • B
    76% (25)
  • C
    3% (1)
  • D
    12% (4)

Explanation

The program scope statement is a comprehensive document that defines the program's deliverables and objectives, and also captures stakeholder concerns, constraints, assumptions, perceived threats, and exclusions. It aligns stakeholder expectations with the program's intended outcomes. A business case focuses on justification and feasibility. A requirements document captures functional or technical requirements. A project charter authorizes a project. The scope statement is the appropriate document for capturing the full range of stakeholder concerns, threats, and program objectives described in the question.

Topics

#Program Scope Management#Program Definition#Stakeholder Engagement#Program Documentation