You are the program manage of HYH Program for your organization. Your program is to create a new sports arena for your city within 12 months. Your program has seven projects and you've worked with all

The correct answer is A. Project charter for each project. The project charter is the document that formally authorizes the project and officially names the project manager, granting them the authority to apply organizational resources to project activities. Even in a program environment where the program manager already knows the projec

Program Life Cycle Management

Question

You are the program manage of HYH Program for your organization. Your program is to create a new sports arena for your city within 12 months. Your program has seven projects and you've worked with all of the project managers before. Even though you've worked with the project managers before you still need to define the authority of the project managers and their projects. What document names the project manager for the project?

Options

  • AProject charter for each project
  • BProgram human resource management plan
  • CProject scope statement
  • DProgram management charter

How the community answered

(43 responses)
  • A
    91% (39)
  • B
    5% (2)
  • C
    2% (1)
  • D
    2% (1)

Explanation

The project charter is the document that formally authorizes the project and officially names the project manager, granting them the authority to apply organizational resources to project activities. Even in a program environment where the program manager already knows the project managers, each project still requires its own charter to formally establish the project and define the PM's authority level. The program human resource management plan (B) describes how resources will be acquired and managed but does not name or authorize specific PMs. The project scope statement (C) defines deliverables and objectives. The program management charter (D) authorizes the program, not individual projects within it. Each project's charter is where the PM is officially named and empowered.