PGMP · Question #309

You are the program manager for your organization and you need to define all of the program resources you'll need for your program. All of the following can be considered a program resource except for

The correct answer is C. A positive risk response. A positive risk response (also called an opportunity response) is a risk management strategy - it is a planned action to exploit, share, enhance, or accept a potential positive risk event. It is not a resource. Resources are the tangible and human inputs consumed or used to produ

Program Life Cycle Management

Question

You are the program manager for your organization and you need to define all of the program resources you'll need for your program. All of the following can be considered a program resource except for which one?

Options

  • AA forklift
  • BMaterials for the installation of a new server
  • CA positive risk response
  • DGary, an application developer

How the community answered

(46 responses)
  • A
    7% (3)
  • B
    2% (1)
  • C
    89% (41)
  • D
    2% (1)

Explanation

A positive risk response (also called an opportunity response) is a risk management strategy - it is a planned action to exploit, share, enhance, or accept a potential positive risk event. It is not a resource. Resources are the tangible and human inputs consumed or used to produce program deliverables: equipment such as a forklift (A), materials like server components (B), and personnel like Gary the developer (D) are all classic examples of program resources. Risk responses belong to the risk management domain, not the resource management domain. This question tests the ability to distinguish between resource types and risk management artifacts.

Topics

#Program Resources#Resource Management#Program Planning#Risk Management

Community Discussion

No community discussion yet for this question.