PGMP · Question #158

Which of the following represents the duration of activities against a calendar?

The correct answer is C. Gantt chart. A Gantt chart is the standard project management tool that displays activity durations as horizontal bars plotted against a calendar timeline.

Program Life Cycle Management

Question

Which of the following represents the duration of activities against a calendar?

Options

  • APie chart
  • BScatter chart
  • CGantt chart
  • DPareto chart

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    88% (29)
  • D
    6% (2)

Why each option

A Gantt chart is the standard project management tool that displays activity durations as horizontal bars plotted against a calendar timeline.

APie chart

A pie chart represents proportional relationships as slices of a circle and contains no time axis or duration information.

BScatter chart

A scatter chart plots individual data points on X-Y axes to show correlations or distributions between two variables, not activity durations.

CGantt chartCorrect

A Gantt chart plots each activity as a bar whose length corresponds to its duration, positioned along a time axis that represents the calendar. This format makes it immediately clear when each activity starts, how long it lasts, and how activities overlap, making it the definitive tool for schedule visualization.

DPareto chart

A Pareto chart is a descending bar chart used in quality management to rank defect types by frequency or impact, not to represent schedule information.

Concept tested: Gantt chart as activity duration scheduling tool

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Gantt chart#Scheduling#Activity Duration#Program Planning Tools