PGMP · Question #159
Robert is the program manager for his organization which operates in a matrix structure. Resources in Robert's program will be utilized on several projects in and out of his program. He wants to be ce
The correct answer is B. Resource management plan. A resource management plan defines how resources will be identified, acquired, scheduled, and coordinated across all projects within a program or organization.
Question
Robert is the program manager for his organization which operates in a matrix structure. Resources in Robert's program will be utilized on several projects in and out of his program. He wants to be certain that all of the resources will be planned accordingly and that the project managers communicate with one another about when the resources will be needed and utilized in the projects. What plan should Robert create along with the project managers to ensure that the resources are scheduled and managed effectively?
Options
- ASchedule management plan
- BResource management plan
- CProgram management calendar
- DResource calendar
How the community answered
(40 responses)- A5% (2)
- B73% (29)
- C8% (3)
- D15% (6)
Why each option
A resource management plan defines how resources will be identified, acquired, scheduled, and coordinated across all projects within a program or organization.
A schedule management plan governs how the project schedule is developed, maintained, and controlled - it does not address cross-project resource coordination.
The resource management plan establishes policies and procedures for how resources are planned, allocated, and communicated across multiple projects, which is precisely what Robert needs in a matrix environment where resources move between projects inside and outside his program. It also defines how project managers will collaborate regarding resource availability and handoffs.
A program management calendar is not a standard PMI planning component for managing resource utilization and communication across project teams.
A resource calendar documents the availability windows for specific resources but does not provide the planning framework or communication protocols needed to coordinate resource use across multiple project managers.
Concept tested: Resource management plan in matrix program environment