PFMP · Question #445
Management practices are leveraged by organizational resources and as a portfolio manager, you realize that the correct management of supply and demand with relation to organizational resources is cru
The correct answer is B. None of the options. The correct answer is B - 'None of the options' - which means all listed items ARE organizational resources. Program and project managers (Option A) are human resources. Funds (Option C) are financial resources. Assets (Option D) are physical or intangible organizational resource
Question
Management practices are leveraged by organizational resources and as a portfolio manager, you realize that the correct management of supply and demand with relation to organizational resources is crucial to the success of a portfolio. Which of the following is not an organizational resource?
Options
- AProgram and project managers
- BNone of the options
- CFunds
- DAssets
How the community answered
(17 responses)- B94% (16)
- D6% (1)
Explanation
The correct answer is B - 'None of the options' - which means all listed items ARE organizational resources. Program and project managers (Option A) are human resources. Funds (Option C) are financial resources. Assets (Option D) are physical or intangible organizational resources. In portfolio management, organizational resources encompass people (including program/project managers), financial resources (funds), physical assets, technology, and other capabilities that the organization uses to execute portfolio components. Since every option listed is a valid organizational resource, 'None of the options' is the correct answer to the question of what is NOT an organizational resource.
Topics
Community Discussion
No community discussion yet for this question.