nerdexam
PMI

PFMP · Question #430

Calculate the composite index for the following portfolio having CPI weight = 80% and SPI weight = 20% Larger image

The correct answer is C. 1. The Composite Index is calculated as a weighted average of the Cost Performance Index (CPI) and Schedule Performance Index (SPI) using their respective weights: Composite Index = (CPI × CPI weight) + (SPI × SPI weight). With CPI weight = 80% (0.80) and SPI weight = 20% (0.20)…

Performance

Question

Calculate the composite index for the following portfolio having CPI weight = 80% and SPI weight = 20% Larger image

Options

  • A0.9
  • B1.5
  • C1
  • D1.1

How the community answered

(38 responses)
  • A
    13% (5)
  • B
    3% (1)
  • C
    76% (29)
  • D
    8% (3)

Explanation

The Composite Index is calculated as a weighted average of the Cost Performance Index (CPI) and Schedule Performance Index (SPI) using their respective weights: Composite Index = (CPI × CPI weight) + (SPI × SPI weight). With CPI weight = 80% (0.80) and SPI weight = 20% (0.20), the formula becomes: Composite Index = (CPI × 0.80) + (SPI × 0.20). Based on the data in the referenced table (not visible here), the calculated result equals 1.0 (Option C). A composite index of 1.0 indicates that the portfolio is performing exactly on budget and on schedule in aggregate. Values above 1.0 indicate better-than-planned performance, while values below 1.0 indicate under-performance. This weighted composite gives more emphasis to cost performance (CPI) than schedule performance (SPI).

Topics

#Portfolio Performance Management#Earned Value Management (EVM)#Composite Index#Weighted Average

Community Discussion

No community discussion yet for this question.

Full PFMP Practice