PFMP · Question #431

As you grow older, you gain more experience and things that once seemed hard to assimilate, can become very easy. One junior member of your portfolio management team is confused on the relationship be

The correct answer is A. The provide portfolio oversight process may trigger the other two processes as part of the review. In PMI's Standard for Portfolio Management, the 'Provide Portfolio Oversight' process is a governance and monitoring function that sits above the others. During portfolio reviews, this process evaluates overall portfolio health and performance - and based on its findings, it can

Portfolio Governance

Question

As you grow older, you gain more experience and things that once seemed hard to assimilate, can become very easy. One junior member of your portfolio management team is confused on the relationship between the Optimize, Authorize and Provide Oversight processes. What could your advice to him be?

Options

  • AThe provide portfolio oversight process may trigger the other two processes as part of the review
  • BThe three processes are not related and are in different focus areas
  • CThe Optimize portfolio comes first, then authorize portfolio and finally Provide Portfolio oversight
  • DThe Optimize portfolio process is used to balance the portfolio so that the authorize portfolio and

How the community answered

(38 responses)
  • A
    95% (36)
  • B
    3% (1)
  • D
    3% (1)

Explanation

In PMI's Standard for Portfolio Management, the 'Provide Portfolio Oversight' process is a governance and monitoring function that sits above the others. During portfolio reviews, this process evaluates overall portfolio health and performance - and based on its findings, it can trigger the 'Optimize Portfolio' process (to rebalance components) and/or the 'Authorize Portfolio' process (to approve or reprioritize components). The three processes are interconnected, not isolated, and oversight acts as the catalyst. Option C is incorrect because there is no fixed sequential order; option B is wrong because they are absolutely related.

Topics

#Portfolio processes#Process interdependencies#Portfolio oversight#Portfolio authorization