PFMP · Question #532

Portfolios have a lot of components in them and are executed along an extended lifecycle. For this, as a portfolio manager, you continuously monitor and control the progress and status. What input…

The correct answer is B. Roadmap, Portfolio Management Plan, Portfolio, Portfolio Reports, Portfolio Process Assets. When continuously monitoring and controlling a portfolio, the correct set of inputs includes Portfolio Process Assets rather than Enterprise Environmental Factors or other variants.

Performance

Question

Portfolios have a lot of components in them and are executed along an extended lifecycle. For this, as a portfolio manager, you continuously monitor and control the progress and status. What input can you use to help you with this?

Options

  • ARoadmap, Portfolio Management Plan, Portfolio, Portfolio Reports, Enterprise Environmental
  • BRoadmap, Portfolio Management Plan, Portfolio, Portfolio Reports, Portfolio Process Assets
  • CRoadmap, Portfolio Management Plan, Portfolio, Portfolio Reports, Portfolio Organizational
  • DRoadmap, Portfolio Strategic Plan, Portfolio, Portfolio Reports, Portfolio Process Assets

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    87% (27)
  • C
    3% (1)
  • D
    6% (2)

Why each option

When continuously monitoring and controlling a portfolio, the correct set of inputs includes Portfolio Process Assets rather than Enterprise Environmental Factors or other variants.

ARoadmap, Portfolio Management Plan, Portfolio, Portfolio Reports, Enterprise Environmental

Enterprise Environmental Factors are not listed as a direct input to the Monitor and Control Portfolio Work process; Portfolio Process Assets is the correct fifth input.

BRoadmap, Portfolio Management Plan, Portfolio, Portfolio Reports, Portfolio Process AssetsCorrect

According to the PMI Standard for Portfolio Management, the Monitor and Control Portfolio Work process uses the Roadmap, Portfolio Management Plan, Portfolio, Portfolio Reports, and Portfolio Process Assets as its inputs. Portfolio Process Assets include historical information, lessons learned, and templates that directly support ongoing monitoring activities. This combination aligns precisely with the defined IPECC inputs for this process.

CRoadmap, Portfolio Management Plan, Portfolio, Portfolio Reports, Portfolio Organizational

'Portfolio Organizational' is not a recognized input category in the PMI Portfolio Management Standard.

DRoadmap, Portfolio Strategic Plan, Portfolio, Portfolio Reports, Portfolio Process Assets

The Portfolio Strategic Plan is a separate artifact; the correct document used as an input here is the Portfolio Management Plan, not the Strategic Plan.

Concept tested: Inputs to Monitor and Control Portfolio Work process

Source: https://www.pmi.org/pmbok-guide-standards/foundational/portfolio-management

Topics

#Portfolio Monitoring and Control#Portfolio Management Process Inputs#Portfolio Management Plan#Organizational Process Assets