PFMP Question #390: Real Exam Question with Answer & Explanation

The correct answer is C: Update the roles and responsibilities in the Portfolio Management Plan. See the full explanation below for the reasoning.

Governance

Question

A new project manager was given an assignment on one of the components in your portfolio. What will you do as a portfolio manager in order to align the project manager with the strategic direction and integrate him/her with the work in progress?

Options

  • ALet him check the Project Charter and ask you in the case where he needs your help
  • BLet him check the Portfolio Charter and ask you in the case where he needs your help
  • CUpdate the roles and responsibilities in the Portfolio Management Plan
  • DTrain him on the portfolio management processes

Topics

#Portfolio Governance#Roles and Responsibilities#Portfolio Management Plan#Stakeholder Integration

Community Discussion