Based on input from an organization's senior management, the portfolio manager has removed some components from a portfolio, replaced them with other components, and has rebalanced and reprioritized…

The correct answer is C. Portfolio management plan. When stakeholders express concerns about portfolio rebalancing decisions, the portfolio manager should consult the portfolio management plan, which contains the stakeholder engagement and communication strategies.

Governance

Question

Based on input from an organization's senior management, the portfolio manager has removed some components from a portfolio, replaced them with other components, and has rebalanced and reprioritized the portfolio components. Individuals affected by the changes are expressing mixed reactions to the new portfolio. Which document should the portfolio manager refer to before developing a response plan to address these concerns?

Options

  • AStakeholder matrix
  • BOrganizational chart
  • CPortfolio management plan
  • DPortfolio charter

How the community answered

(27 responses)
  • A
    7% (2)
  • B
    4% (1)
  • C
    78% (21)
  • D
    11% (3)

Why each option

When stakeholders express concerns about portfolio rebalancing decisions, the portfolio manager should consult the portfolio management plan, which contains the stakeholder engagement and communication strategies.

AStakeholder matrix

The stakeholder matrix identifies stakeholders and their interests but does not contain the engagement strategies or communication approaches needed to develop a response plan for concerns.

BOrganizational chart

The organizational chart shows reporting structures and hierarchies but does not provide guidance on how to manage stakeholder reactions or formulate response strategies.

CPortfolio management planCorrect

The portfolio management plan contains the stakeholder management approach, engagement strategies, and communication guidelines that define how the portfolio manager should respond to and manage stakeholder concerns - providing the authoritative framework for developing a response plan to address mixed reactions to portfolio changes.

DPortfolio charter

The portfolio charter authorizes the portfolio and defines high-level objectives but does not contain the detailed stakeholder engagement strategies required for developing a response plan.

Concept tested: Portfolio management plan stakeholder engagement guidance

Topics

#Portfolio management plan#Stakeholder engagement#Portfolio governance#Change management