You have just completed portfolio optimization and want to allocate resources to selected portfolio components. Which process should you follow?

The correct answer is D. Authorize Portfolio. The 'Authorize Portfolio' process is the formal step where approved portfolio components receive official authorization to proceed along with the allocation of organizational resources (budget, personnel, assets). After optimization determines which components are included in…

Governance

Question

You have just completed portfolio optimization and want to allocate resources to selected portfolio components. Which process should you follow?

Options

  • AManage Supply and Demand
  • BDevelop Portfolio Management Plan
  • CProvide Portfolio Oversight
  • DAuthorize Portfolio

How the community answered

(60 responses)
  • A
    3% (2)
  • B
    2% (1)
  • D
    95% (57)

Explanation

The 'Authorize Portfolio' process is the formal step where approved portfolio components receive official authorization to proceed along with the allocation of organizational resources (budget, personnel, assets). After optimization determines which components are included in the portfolio, 'Authorize Portfolio' is the process that grants them the green light and assigns resources. 'Manage Supply and Demand' deals with ongoing capacity alignment, not initial resource allocation post-optimization.