PMIPMI
PFMP · Question #307
PFMP Question #307: Real Exam Question with Answer & Explanation
The correct answer is A: Portfolio Strategic Plan, Enterprise Environmental Factors, Portfolio Process Assets. See the full explanation below for the reasoning.
Governance
Question
Chartering a portfolio is a major step in getting the needed authorizations to execute the portfolio. Your are currently developing the charter and considering the following inputs
Options
- APortfolio Strategic Plan, Enterprise Environmental Factors, Portfolio Process Assets
- BPortfolio Strategic Plan, Enterprise Environmental Factors, Portfolio Process Assets, Portfolio
- CPortfolio Strategic Plan, Enterprise Environmental Factors, Portfolio Process Assets, Portfolio
- DPortfolio Strategic Plan, Enterprise Environmental Factors, Portfolio Process Assets, Portfolio
Topics
#Portfolio Charter#Portfolio Inputs#Portfolio Governance#Portfolio Definition