Chartering a portfolio is a major step in getting the needed authorizations to execute the portfolio. Your are currently developing the charter and considering the following inputs
The correct answer is A. Portfolio Strategic Plan, Enterprise Environmental Factors, Portfolio Process Assets. The correct inputs to Develop Portfolio Charter are: Portfolio Strategic Plan (which defines the strategic objectives the charter must align with), Enterprise Environmental Factors (which include organizational culture, market conditions, and constraints), and Portfolio Process A
Question
Chartering a portfolio is a major step in getting the needed authorizations to execute the portfolio. Your are currently developing the charter and considering the following inputs
Options
- APortfolio Strategic Plan, Enterprise Environmental Factors, Portfolio Process Assets
- BPortfolio Strategic Plan, Enterprise Environmental Factors, Portfolio Process Assets, Portfolio
- CPortfolio Strategic Plan, Enterprise Environmental Factors, Portfolio Process Assets, Portfolio
- DPortfolio Strategic Plan, Enterprise Environmental Factors, Portfolio Process Assets, Portfolio
How the community answered
(32 responses)- A94% (30)
- B3% (1)
- C3% (1)
Explanation
The correct inputs to Develop Portfolio Charter are: Portfolio Strategic Plan (which defines the strategic objectives the charter must align with), Enterprise Environmental Factors (which include organizational culture, market conditions, and constraints), and Portfolio Process Assets (which include templates, historical information, and lessons learned). Option A correctly lists only these three. Options B, C, and D all include 'Portfolio' as an additional input - this is incorrect because the Portfolio document is an output of later processes (Define Portfolio). The charter is created early to authorize the portfolio; the portfolio itself has not yet been formally defined at this stage.