PMIPMI
PFMP · Question #195
PFMP Question #195: Real Exam Question with Answer & Explanation
The correct answer is D: management plan.. See the full explanation below for the reasoning.
Governance
Question
After receiving a regular resource utilization report, the portfolio manager has identified two portfolio components that are competing for the same key resource. The unavailability of this resource has the potential to delay both projects. Some stakeholders have complained to the executive sponsor that they were not made aware of the situation. In order to ensure that similar situations are properly addressed in the future, the portfolio manager should update the portfolio:
Options
- Astrategic plan.
- Bresource management plan.
- Cgovernance plan.
- Dmanagement plan.
Topics
#Portfolio Management Plan#Resource Conflict Resolution#Stakeholder Communication#Governance Processes
Community Discussion
No community discussion yet for this question.