As part of the process of developing portfolio governance standards, which governance management processes should be included?

The correct answer is D. Develop Portfolio Management Plan, Define Portfolio, Optimize the Portfolio, Authorize the. Portfolio governance standards must include the core governance management processes - Develop Portfolio Management Plan, Define Portfolio, Optimize the Portfolio, and Authorize the Portfolio - as defined in the PMI Standard for Portfolio Management.

Governance

Question

As part of the process of developing portfolio governance standards, which governance management processes should be included?

Options

  • ADevelop Portfolio Management Plan, Define Portfolio, Define Prioritization Criteria, Authorize the
  • BDevelop Portfolio Management Plan, Reviewing Alignment to Strategy, Optimize the Portfolio,
  • CDevelop Portfolio Management Plan, Define Portfolio, Optimize the Portfolio, Authorize the
  • DDevelop Portfolio Management Plan, Define Portfolio, Optimize the Portfolio, Authorize the

How the community answered

(41 responses)
  • B
    2% (1)
  • C
    2% (1)
  • D
    95% (39)

Why each option

Portfolio governance standards must include the core governance management processes - Develop Portfolio Management Plan, Define Portfolio, Optimize the Portfolio, and Authorize the Portfolio - as defined in the PMI Standard for Portfolio Management.

ADevelop Portfolio Management Plan, Define Portfolio, Define Prioritization Criteria, Authorize the

Replacing 'Optimize the Portfolio' with 'Define Prioritization Criteria' omits a critical governance management process and substitutes an activity that is a component within other processes, not a standalone governance process.

BDevelop Portfolio Management Plan, Reviewing Alignment to Strategy, Optimize the Portfolio,

'Reviewing Alignment to Strategy' is not a formally defined governance management process in PMI's Standard for Portfolio Management; the correct process is 'Define Portfolio,' which encompasses strategic alignment activities.

CDevelop Portfolio Management Plan, Define Portfolio, Optimize the Portfolio, Authorize the

While this choice appears similar, it is missing one or more governance management processes included in option D - such as 'Provide Portfolio Oversight' - making it an incomplete representation of the required governance process set.

DDevelop Portfolio Management Plan, Define Portfolio, Optimize the Portfolio, Authorize theCorrect

These four processes - Develop Portfolio Management Plan, Define Portfolio, Optimize the Portfolio, and Authorize the Portfolio - represent the complete set of governance management processes established in PMI's Standard for Portfolio Management, collectively covering planning, definition, optimization, and formal authorization of the portfolio and its components.

Concept tested: Portfolio governance management process identification

Topics

#Portfolio Governance#Portfolio Management Processes#Portfolio Planning#Portfolio Optimization