A new project manager has been assigned to a project in an approved portfolio. What should the portfolio manager do to ensure that the new project manager will be able to support the portfolio…

The correct answer is D. Update the portfolio management plan to reflect the new assignment. When a new project manager is assigned to a portfolio component, the portfolio manager's primary responsibility is to update the portfolio management plan to reflect the change in roles and responsibilities.

Portfolio Governance

Question

A new project manager has been assigned to a project in an approved portfolio. What should the portfolio manager do to ensure that the new project manager will be able to support the portfolio management requirements and processes?

Options

  • ATrain the project manager on portfolio management processes.
  • BTrain the project manager on project management processes.
  • CRevise documentation and update the current portfolio reports.
  • DUpdate the portfolio management plan to reflect the new assignment.

How the community answered

(33 responses)
  • A
    18% (6)
  • B
    6% (2)
  • C
    6% (2)
  • D
    70% (23)

Why each option

When a new project manager is assigned to a portfolio component, the portfolio manager's primary responsibility is to update the portfolio management plan to reflect the change in roles and responsibilities.

ATrain the project manager on portfolio management processes.

While the new project manager may need orientation to portfolio processes, providing training is not the portfolio manager's primary action - updating the governance documentation that defines the manager's responsibilities takes precedence.

BTrain the project manager on project management processes.

Training on project management processes is the responsibility of the project manager's direct supervisor or PMO, not the portfolio manager, and does not address portfolio management requirements.

CRevise documentation and update the current portfolio reports.

Revising documentation and updating current portfolio reports addresses operational outputs and does not fulfill the governance responsibility of updating the plan to reflect the new role assignment.

DUpdate the portfolio management plan to reflect the new assignment.Correct

The portfolio management plan documents governance structures, roles, responsibilities, and resource assignments for the portfolio; updating it to reflect the new project manager ensures accurate accountability, reporting lines, and formal integration of the new manager into portfolio processes, which is the portfolio manager's governance responsibility.

Concept tested: Portfolio management plan updates for role changes

Topics

#Portfolio Management Plan#Portfolio Governance#Roles and Responsibilities#Stakeholder Integration