Question
A new project manager has been assigned to a project in an approved portfolio. What should the portfolio manager do to ensure that the new project manager will be able to support the portfolio management requirements and processes?
Options
- ATrain the project manager on portfolio management processes.
- BTrain the project manager on project management processes.
- CRevise documentation and update the current portfolio reports.
- DUpdate the portfolio management plan to reflect the new assignment.