The correct answer is D: Update the portfolio management plan to reflect the new assignment.. See the full explanation below for the reasoning.

Portfolio Governance

Question

A new project manager has been assigned to a project in an approved portfolio. What should the portfolio manager do to ensure that the new project manager will be able to support the portfolio management requirements and processes?

Options

  • ATrain the project manager on portfolio management processes.
  • BTrain the project manager on project management processes.
  • CRevise documentation and update the current portfolio reports.
  • DUpdate the portfolio management plan to reflect the new assignment.

Topics

#Portfolio Management Plan#Portfolio Governance#Roles and Responsibilities#Stakeholder Integration

Community Discussion

No community discussion yet for this question.

Full PFMP PracticeBrowse All PFMP Questions