The correct answer is C: Openly discuss the issue with the stakeholders and its impact on their interests.. See the full explanation below for the reasoning.

Portfolio Stakeholder Engagement

Question

Several stakeholders have recently been very busy with a new corporate initiative and begin to miss portfolio meetings. Portfolio decisions have been delayed, which may have an impact on the overall portfolio performance. Which action should the portfolio manager take in order to reengage these stakeholders?

Options

  • ASend a memo to the stakeholders to comply with the portfolio management plan.
  • BDiscuss the issue with the portfolio sponsor and ask for support.
  • COpenly discuss the issue with the stakeholders and its impact on their interests.
  • DFormally escalate the issue to the portfolio governance board.

Topics

#Stakeholder Engagement#Portfolio Communication#Conflict Resolution#Decision Making