You plan to create a service activity. You need to identify which types of participant can have defined work hours. Which two participant types should you identify? Each correct answer presents a…
The correct answer is C. user D. equipment. See the full explanation below for the reasoning.
Question
You plan to create a service activity. You need to identify which types of participant can have defined work hours. Which two participant types should you identify? Each correct answer presents a complete solution.
Exhibit
Options
- Aresource group
- Bsite
- Cuser
- Dequipment
How the community answered
(65 responses)- A18% (12)
- B11% (7)
- C71% (46)