You create a service level agreement (SLA) that wilt fail after seven days. You select a service calendar that uses 24-hour work days and no holidays. Saturday and Sunday are configured to be…

The correct answer is A. 5 days. See the full explanation below for the reasoning.

Question

You create a service level agreement (SLA) that wilt fail after seven days. You select a service calendar that uses 24-hour work days and no holidays. Saturday and Sunday are configured to be non-working days. If no action is taken, how many calendar days can pass before the SLA fails?

Options

  • A5 days
  • B7 days
  • C9 days
  • D11 days

How the community answered

(26 responses)
  • A
    81% (21)
  • B
    12% (3)
  • C
    4% (1)
  • D
    4% (1)