Question

You create a service level agreement (SLA) that wilt fail after seven days. You select a service calendar that uses 24-hour work days and no holidays. Saturday and Sunday are configured to be non-working days. If no action is taken, how many calendar days can pass before the SLA fails?

Options

  • A5 days
  • B7 days
  • C9 days
  • D11 days

Unlock MB2-718 to see the answer