MB-335 · Question #215
A manufacturing company uses the production control module in Dynamics 365 Supply Chain Management. A production planner at the company must prevent resources from being allocated to multiple tasks…
The correct answer is C. Exclusive. Operations resources are assigned to activities when a project or a production is scheduled. On the Resources page, you can define several properties that control how capacity reservations *-> Exclusive - Set this option to Yes if you don't want the operations resource to be…
Question
A manufacturing company uses the production control module in Dynamics 365 Supply Chain Management. A production planner at the company must prevent resources from being allocated to multiple tasks simultaneously when the resources are already engaged in a task. You need to enable the property on the operation resource master. Which property should you enable?
Options
- AFinite capacity
- BBottleneck resource
- CExclusive
- DJob scheduling
How the community answered
(58 responses)- A17% (10)
- B3% (2)
- C71% (41)
- D9% (5)
Explanation
Operations resources are assigned to activities when a project or a production is scheduled. On the Resources page, you can define several properties that control how capacity reservations *-> Exclusive - Set this option to Yes if you don't want the operations resource to be available for another job or operation until the current production is completed. In this case, the operations resource can't be used even if there are gaps in the resource's run time. https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/operations-