nerdexam
Microsoft

MB-335 · Question #214

Drag and Drop Question A manufacturing company plans to implement Dynamics 365 Supply Chain Management. A production order has two operations that occur at the same workstation. The first operation…

The correct answer is Estimation; Manual. D365 SCM Reservation Policies - Exam Explanation The Scenario Summary Two operations on one production order: Op 1: Raw materials → Subcomponent (BOM-driven) Op 2: Subcomponent → Finished good Two reservation requirements → two configuration slots. --- Correct Arrangement |…

Configure production control

Question

Drag and Drop Question A manufacturing company plans to implement Dynamics 365 Supply Chain Management. A production order has two operations that occur at the same workstation. The first operation has a BOM that creates a subcomponent. The subcomponent is then used in the second operation to create the finished good. The production manager wants to ensure that: - production items are physically linked to the production order at the last possible moment. - the manager has the ability to manage the reservation of the subcomponent that has not yet been produced. The system must not take action on the subcomponent on the manager's behalf. You must configure the reservation policies. What should you configure? To answer, move the appropriate configurations to the correct requirements. You may use each configuration once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content. NOTE: Each correct selection is worth one point. Answer:

Exhibit

MB-335 question #214 exhibit

Answer Area

Drag items

StartManualEstimation

Correct arrangement

  • Estimation
  • Manual

Explanation

D365 SCM Reservation Policies - Exam Explanation

The Scenario Summary

Two operations on one production order:

  • Op 1: Raw materials → Subcomponent (BOM-driven)
  • Op 2: Subcomponent → Finished good

Two reservation requirements → two configuration slots.


Correct Arrangement

PositionRequirementAnswer
1Physically link production items at the last possible momentEstimation
2Manager manages subcomponent reservation; system must not actManual

Why Each Placement is Correct

Position 1 - Estimation

In D365 SCM, the Estimation flushing/reservation principle means the system physically marks on-hand inventory against the production order when the Estimate step is run on the order lifecycle.

The production order lifecycle is: Created → Estimated → Scheduled → Released → Started

"Estimation" represents the last point in the pre-production planning phase where the physical link is established. The system waits until this definitive planning step - rather than at order creation - to commit inventory. This satisfies "last possible moment" in the context of planning commitment before execution begins.

Key technical point: Estimation creates the formal material requirement calculation and marks the physical on-hand quantities against the order, without prematurely consuming inventory.


Position 2 - Manual

The subcomponent does not yet exist in inventory (it is produced by Operation 1). An automatic reservation policy would either fail or cause system-generated actions on non-existent stock - both violating the requirement.

Manual means the system takes zero automatic action. The production manager retains full control to create the reservation once Operation 1 outputs the subcomponent. This directly satisfies:

  • "Manager has ability to manage the reservation"
  • "System must not take action on the manager's behalf"

Why "Start" is the Wrong Choice (Common Mistake)

Start is a distractor because it sounds logical - "reserve when production starts." However:

  • For requirement 1: Start triggers consumption during production execution, not during planning. It doesn't represent a pre-production physical link.
  • For requirement 2: Start would cause the system to automatically consume/flush the subcomponent when production starts - directly violating the "system must not take action" constraint.

The misconception: Confusing flushing (consumption timing) with reservation (inventory commitment). Manual controls reservation ownership; Estimation controls when the planning system formally links physical inventory.

Topics

#reservation policies#production orders#subcomponent reservation#BOM linkage

Community Discussion

No community discussion yet for this question.

Full MB-335 Practice