MB-335 · Question #214
Drag and Drop Question A manufacturing company plans to implement Dynamics 365 Supply Chain Management. A production order has two operations that occur at the same workstation. The first operation…
The correct answer is Estimation; Manual. D365 SCM Reservation Policies - Exam Explanation The Scenario Summary Two operations on one production order: Op 1: Raw materials → Subcomponent (BOM-driven) Op 2: Subcomponent → Finished good Two reservation requirements → two configuration slots. --- Correct Arrangement |…
Question
Exhibit
Answer Area
Drag items
Correct arrangement
- Estimation
- Manual
Explanation
D365 SCM Reservation Policies - Exam Explanation
The Scenario Summary
Two operations on one production order:
- Op 1: Raw materials → Subcomponent (BOM-driven)
- Op 2: Subcomponent → Finished good
Two reservation requirements → two configuration slots.
Correct Arrangement
| Position | Requirement | Answer |
|---|---|---|
| 1 | Physically link production items at the last possible moment | Estimation |
| 2 | Manager manages subcomponent reservation; system must not act | Manual |
Why Each Placement is Correct
Position 1 - Estimation
In D365 SCM, the Estimation flushing/reservation principle means the system physically marks on-hand inventory against the production order when the Estimate step is run on the order lifecycle.
The production order lifecycle is: Created → Estimated → Scheduled → Released → Started
"Estimation" represents the last point in the pre-production planning phase where the physical link is established. The system waits until this definitive planning step - rather than at order creation - to commit inventory. This satisfies "last possible moment" in the context of planning commitment before execution begins.
Key technical point: Estimation creates the formal material requirement calculation and marks the physical on-hand quantities against the order, without prematurely consuming inventory.
Position 2 - Manual
The subcomponent does not yet exist in inventory (it is produced by Operation 1). An automatic reservation policy would either fail or cause system-generated actions on non-existent stock - both violating the requirement.
Manual means the system takes zero automatic action. The production manager retains full control to create the reservation once Operation 1 outputs the subcomponent. This directly satisfies:
- "Manager has ability to manage the reservation"
- "System must not take action on the manager's behalf"
Why "Start" is the Wrong Choice (Common Mistake)
Start is a distractor because it sounds logical - "reserve when production starts." However:
- For requirement 1: Start triggers consumption during production execution, not during planning. It doesn't represent a pre-production physical link.
- For requirement 2: Start would cause the system to automatically consume/flush the subcomponent when production starts - directly violating the "system must not take action" constraint.
The misconception: Confusing flushing (consumption timing) with reservation (inventory commitment). Manual controls reservation ownership; Estimation controls when the planning system formally links physical inventory.
Topics
Community Discussion
No community discussion yet for this question.
