You have a product that can be manufactured on two different production lines in the same warehouse. You create resources and then create individual input locations for the resources. You create two…
The correct answer is A. Select resource consumption and the operation for each line. You've hit your limit · resets 4am (America/New_York)
Configure production prerequisites
Question
You have a product that can be manufactured on two different production lines in the same warehouse. You create resources and then create individual input locations for the resources. You create two routes. Each route uses different resources. Materials are staged for consumption in different locations based on the resources being utilized for production. You need to set up the formula to consume the goods from the correct line-side location. What should you do?
Options
- ASelect resource consumption and the operation for each line.
- BSelect the plan group and consumption operation for each line.
- CSpecify a site in the formula header.
- DSelect a warehouse and consumption operation for each line.
How the community answered
(42 responses)- A79% (33)
- B12% (5)
- C5% (2)
- D5% (2)
Explanation
You've hit your limit · resets 4am (America/New_York)