CompTIA
JK0-017 · Question #99
A project team has determined it will need to source data from a system that was not part of the project scope. The role of the project manager is to analyze which of the following impacts?
The correct answer is D. Schedule, budget, and quality. See the full explanation below for the reasoning.
Question
A project team has determined it will need to source data from a system that was not part of the project scope. The role of the project manager is to analyze which of the following impacts?
Options
- ATechnical design, schedule, and budget
- BBusiness process impacts and resourcing
- CNew software and hardware requirements
- DSchedule, budget, and quality
How the community answered
(33 responses)- A3% (1)
- B6% (2)
- C12% (4)
- D79% (26)
Community Discussion
No community discussion yet for this question.