JK0-017 · Question #97
The business stakeholder has been engaged late and has just had a chance to review the approved requirements. Consequently, it has been identified that there are a number of gaps in the requirements…
The correct answer is A. Initiate change control. See the full explanation below for the reasoning.
Question
The business stakeholder has been engaged late and has just had a chance to review the approved requirements. Consequently, it has been identified that there are a number of gaps in the requirements which are critical to the stakeholder's business unit. Which of the following actions should the project manager take?
Options
- AInitiate change control
- BFollow communications plan
- CManage project quality
- DPrepare a performance report
How the community answered
(55 responses)- A71% (39)
- B5% (3)
- C9% (5)
- D15% (8)