JK0-017 · Question #92

Which of the following MUST be submitted as part of a project change request?

The correct answer is D. Financial impact analysis. See the full explanation below for the reasoning.

Question

Which of the following MUST be submitted as part of a project change request?

Options

  • ARequest for information
  • BProject charter
  • CUpdated detailed design
  • DFinancial impact analysis

How the community answered

(44 responses)
  • A
    2% (1)
  • B
    11% (5)
  • C
    5% (2)
  • D
    82% (36)