As part of the business case, which of the following criteria will drive a feasibility study to be performed?

The correct answer is D. Project has never been done before. See the full explanation below for the reasoning.

Question

As part of the business case, which of the following criteria will drive a feasibility study to be performed?

Options

  • ALow complexity project
  • BAligns with the provided RFP
  • CThere is a legal/regulatory requirement
  • DProject has never been done before

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    5% (2)
  • C
    16% (6)
  • D
    74% (28)