JK0-017 · Question #87
Which of the following components of a project charter include identifying important milestones of the project?
The correct answer is A. Key project deliverables. See the full explanation below for the reasoning.
Question
Which of the following components of a project charter include identifying important milestones of the project?
Options
- AKey project deliverables
- BHigh level assumptions
- CIdentify stakeholders
- DHigh level constraints
How the community answered
(59 responses)- A71% (42)
- B8% (5)
- C3% (2)
- D17% (10)