Which of the following project plan components would include information regarding the management of issues?

The correct answer is A. Project Management Plan. See the full explanation below for the reasoning.

Question

Which of the following project plan components would include information regarding the management of issues?

Options

  • AProject Management Plan
  • BHuman Resources Plan
  • CRisk Management Plan
  • DScope Management Plan

How the community answered

(29 responses)
  • A
    83% (24)
  • B
    3% (1)
  • C
    3% (1)
  • D
    10% (3)