Which of the following activities would be considered a project?
The correct answer is C. Directing a team of developers to create a software program. See the full explanation below for the reasoning.
Question
Which of the following activities would be considered a project?
Options
- AProviding on-going support of an organization's software product
- BUpdating an organization's antivirus software
- CDirecting a team of developers to create a software program
- DAny activity with the express purpose of generating revenue
How the community answered
(27 responses)- A7% (2)
- B4% (1)
- C74% (20)
- D15% (4)
Community Discussion