Which of the following activities would be considered a project?

The correct answer is C. Directing a team of developers to create a software program. See the full explanation below for the reasoning.

Question

Which of the following activities would be considered a project?

Options

  • AProviding on-going support of an organization's software product
  • BUpdating an organization's antivirus software
  • CDirecting a team of developers to create a software program
  • DAny activity with the express purpose of generating revenue

How the community answered

(27 responses)
  • A
    7% (2)
  • B
    4% (1)
  • C
    74% (20)
  • D
    15% (4)