JK0-017 · Question #6

Which of the following would be included in the project charter? (Select TWO).

The correct answer is A. Project description E. High level business case. See the full explanation below for the reasoning.

Question

Which of the following would be included in the project charter? (Select TWO).

Options

  • AProject description
  • BRisk management plan
  • CChange management plan
  • DStatement of Work (SOW)
  • EHigh level business case

How the community answered

(27 responses)
  • A
    81% (22)
  • B
    11% (3)
  • C
    4% (1)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.