Question

A company is replacing their file server with a new one. During the data migration, the old file server experiences critical hardware failure. The data migration cannot continue until the hardware is replaced. This repair will put the project behind schedule by a week. Which of the following actions should the project manager do FIRST?

Options

  • APrepare performance report
  • BManage the issue
  • CSchedule a meeting
  • DUpdate communication plan

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    83% (29)
  • C
    9% (3)
  • D
    3% (1)