Which of the following would a project manager organize and implement in order to provide decision oversight to scope changes?
The correct answer is C. Change control board. See the full explanation below for the reasoning.
Question
Which of the following would a project manager organize and implement in order to provide decision oversight to scope changes?
Options
- ARequest for Proposal (RFP)
- BQuality management plan
- CChange control board
- DVersion control system
How the community answered
(34 responses)- A3% (1)
- B15% (5)
- C76% (26)
- D6% (2)