Which of the following is created using the work breakdown structure (WBS) as an input?
The correct answer is A. Procurement management plan. See the full explanation below for the reasoning.
Question
Which of the following is created using the work breakdown structure (WBS) as an input?
Options
- AProcurement management plan
- BVendor selection criteria
- CProject scope statement
- DProject charter
How the community answered
(32 responses)- A75% (24)
- B13% (4)
- C9% (3)
- D3% (1)