JK0-017 · Question #470
The project sponsor indicates that one of the key stakeholders is very unhappy with the project schedule. The other stakeholders are happy with the schedule. Which of the following is the MOST…
The correct answer is B. The project manager did not obtain buy-in from the stakeholder. See the full explanation below for the reasoning.
Question
The project sponsor indicates that one of the key stakeholders is very unhappy with the project schedule. The other stakeholders are happy with the schedule. Which of the following is the MOST likely reason why the stakeholder is unhappy with the schedule?
Options
- AThe stakeholder has unrealistic expectations.
- BThe project manager did not obtain buy-in from the stakeholder.
- CThe project manager did not discuss the schedule with the stakeholders.
- DThe project manager did not schedule the project team appropriately.
How the community answered
(37 responses)- A5% (2)
- B73% (27)
- C16% (6)
- D5% (2)