JK0-017 · Question #468
A key stakeholder has asked the project manager to complete the project a week earlier than expected. To accomplish this objective, the project manager will have to ask the project team to work…
The correct answer is C. Obtain an approved change control document before changing the project schedule. See the full explanation below for the reasoning.
Question
A key stakeholder has asked the project manager to complete the project a week earlier than expected. To accomplish this objective, the project manager will have to ask the project team to work overtime, which will increase the cost of the project. Which of the following should be the NEXT step?
Options
- AAsk the key stakeholder for more funding for the project.
- BAsk the project team to work overtime to finish the project.
- CObtain an approved change control document before changing the project schedule.
- DAgree to complete the project using the new schedule.
How the community answered
(39 responses)- A3% (1)
- B10% (4)
- C82% (32)
- D5% (2)
Community Discussion
No community discussion yet for this question.