Changing the project schedule to prevent a known risk is an example of which of the following risk responses?
The correct answer is B. Avoidance. See the full explanation below for the reasoning.
Question
Changing the project schedule to prevent a known risk is an example of which of the following risk responses?
Options
- AMitigation
- BAvoidance
- CAcceptance
- DTransference
How the community answered
(36 responses)- A14% (5)
- B72% (26)
- C8% (3)
- D6% (2)